CDM 2015 Applies to Fit-Outs and Refurbishments

Most Clients Don't Realise…

You are commissioning an office fit-out. No groundworks. No structural changes. No demolition. Is CDM 2015 relevant?

Yes. Completely.

This is one of the questions we are asked most frequently by commercial clients — particularly those managing property portfolios or commissioning their first significant workplace project.

CDM 2015 defines construction work broadly. It includes fit-outs, refurbishments, M&E installations, internal alterations, and maintenance work. If contractors are on site doing physical work to a building or structure, CDM applies.

That means appointing a Principal Designer and Principal Contractor in writing if more than one contractor is involved, providing pre-construction information, ensuring a Construction Phase Plan is in place before work begins, and maintaining oversight throughout.

The risk for clients commissioning through a main contractor on a design-and-build basis is assuming the contractor absorbs all CDM responsibility. They do not. The client remains a duty holder regardless of the procurement route.

Whether it is a Category A shell finish or a complex Cat B office with raised floors, AV, and M&E integration — CDM applies from the point of appointment.

If you are about to appoint a fit-out contractor on a multi-contractor project and haven't taken advice on your CDM position, now is the time to do so.

Get your free Client Guide to CDM 2015 here: cdm2015.co.uk/resource-download